Pineland Heights – Asphalt Replacement Schedule

 In PINELAND HEIGHTS

ASPHALT REPLACEMENT SCHEDULE

Dear Owner(s) and Tenant(s):

The HOA has contracted J & M Paving to replace the asphalt throughout the community. This is going to be an arduous task but with cooperation from all owners and tenants we can get this done with little to no discord.
The contractor has alerted us that they will start on June 25th. Here is the proposed schedule for prepping & scraping the lots.

You MUST have all vehicles completely out of these lots by 8am on the day listed!!!!!! YOU MAY PARK IN THE GRASS AREAS. IF YOUR VEHICLE IS NOT MOVED ON TIME AND IS BLOCKING WORK, THE HOA MAY HAVE THE CAR TOWED AT THE OWNERS EXPENSE. You can park on the lots once the scraping is completed (probably by the next day). Homeowner’s NOTIFY YOUR TENANTS!

JUNE 25th: units 279, 277, 275, 273, 271, 269, 267, 265, 263, 261, 259, 257, 255, 253, 251, 249, 247, 245
JUNE 26th: units 243, 241, 239, 237, 235, 233, 231, 229, 227, 225, 223, 221, 219, 217, 215, 213, 211, 209
JUNE 27TH: units 207, 205, 203, 201, 199, 197, 195, 193, 191, 189, 187, 185, 183, 181, 179, 177, 175, 173
JUNE 28th: units 171, 169, 167, 165, 163, 161, 184, 186, 188, 190, 192, 194, 196, 198, 200, 202, 204, 206
JUNE 29th: units 208, 210, 212, 214, 216, 218, 220, 222, 224, 226, 228, 230, 232, 234, 236, 238, 240, 242
JUNE 30th: units 244, 246, 248, 250, 252, 254, 256, 258, 260, 262, 264, 266, 268, 270, 272, 274, 276, 278

Our plan is to have the parking lots scraped and rolled during this week. The company will come back to lay the asphalt during the week of JULY 9th. YOU WILL HAVE TO STAY OFF THE NEW APHALT FOR UP TO 48 HOURS WHILE IT CURES. AGAIN PARKING ON THE GRASS IS ACCEPTABLE DURING THIS TIME!

This project is going to take everyone working together and cooperating with the HOA and contractor. The repaving is a long needed project that will make a huge difference in the overall appearance of your community.
If the weather cooperates and all factors work just right, the job should only take about 2 weeks to complete.
If you have any questions, please contact me at afitch@nullcmgcharleston.com.
Thank you in advance for your cooperation.